Field Ops Memo 2010-11A: BEACON 3.0 User Acceptance Testing (UAT)
Overview
BEACON 3.0 User Acceptance Testing (UAT) is designed to test the typical
transactions encountered by DTA field and Central Office users, as well as
external agencies that interface with BEACON on a daily basis.
Testing is being conducted at TAOs and Central Office by staff who have volunteered and been trained to test the new system. Effective January 16, 2010, BEACON 2.0 data was converted into the BEACON 2.0 Training application. Therefore BEACON 2.0 Training will contain information only as current as January 16, 2010.
Phase 1 of UAT began on January 19, 2010, and Phase 2 began on February 1, 2010.
Purpose
The purpose of this memo is to describe the preparation for and outline the
procedures to be followed in the process for BEACON 3.0 UAT. To that end
a process has been developed and a number of tools have been created to
monitor the testing and communicate any issues that require resolution. To
prepare for UAT, over 500 test scenarios have been developed. A UAT Test
Scenario Inventory document and a Caseload Profile document have been
created for each UAT tester with a caseload. These documents have been
uploaded to the R: Drive for each TAO participating in the testing process.